PSAS/ news/ 2007-04-25 - Re-baselining LV2b

Airframe To do


Airframe Timeline


Total: 6 weeks (6/6) - 12 weeks (7/18) - 18 weeks (8/29)

Action Items


Avionics Team to do Pre-launch ==============================

New Systems


Dust off


Timeline


Total: 12w (7/18)

Action Items


Communication Team to do Pre-launch ===================================

Software to do Pre-launch =========================

Ground Team to do Pre-launch ============================

Decisions =========

So, we decided to go with a launch date between the best and mid-case. Which is probably still optimistic (!). But now we have a real timeline, which is nice: it's time to get to work!