Master Count Down list
The Master count down checklist is broken into phases (Set-up, Prep, Count-down, count-up, tear down) for each of the teams involved (Tower, LCM, airframe, payload, avionics, site Ops)
PDX Prep
tower team
[] verify tower packing list
LCM Team
[] verify LCM packing list
Site Org and layout
[] Verify Site Ops and Misc packing lists
[] Make CD mirror of latest PSAS TWIKI site
[] Rent porta-potties
[] rent large tent (10x20)
[] obtain two banquet tables
[] arrange rides
[] arrange food
[] Arrange camping and land use permissions
L minus one day
Tower
[] find suitable flat area on acess road to place tower
[] measure distance from Close-out area to tower (800 foot minimum)
[] Drop tower and support equipment on site
[] erect tower
[] Attach outriggers to tower for initial stabilization
Launch Control Module
[] Locate LCM at away site (approx 2 mi?)
[] Stabilize truck suspension
[] unpack LCM
[] Organize interior of LCM
[] Bring Generator on line
[] Bring up LCM computers, lights, and radios
Launch Site organization and layout
[] Place signs at intersections directing personnel to site
[] Place initial "information" sign at entrance to operations
[] Place porta-potties
[] mark critical areas with caution and danger tape
[] Set up tables, chairs, awnings, etc
[]Mark camping, spectator, parking, and restricted areas with sign
t minus 4 hours
Tower
[] Radio Check with LCM
[] Finish tower assembly
[] Raise and lower tower once as trial
[] power up tower computer
[] test fire ingiters from LCM
launch Vehicle
[] Radio check with LCM
[] Prep motor
[] Prep recovery system
[] prep airframe and launch lugs
[] integrate recovery system to airframe
Payload/Flight computer
[] Integrate FC to vehicle
[] Verify FC operation
[] Verify IMU operation
[] Verify DTMF operation
[] Verify Video operation
[] Verify tower to LCM datalink
[] Verify payload to LCM datalink
[] LCM participates in igniter test
[] Integrate payload into vehicle
Media and Spectators
[] Guide media and spectators to appropriate locations
[] Answer questions
[] Structure parking
T minus 2 hours
[] integrate motor to vehicle
[] Integrate nosecone to vehicle
[] integrate vehicle to launch tower
[] test vehicle/launch rail slide
T minus 60
[] _LCM_ Activat FAA Waiver at T minus 60 minutes
[] _LCM_ Radio check with all teams
[] _LCM_ Telemetry Checks
[] _Tower_ set up near cameras
[] _Tower_ Close-out crew falls back to safe zone
[] _Tower_ Alert LCM if aircraft spotted in launch area
T minus 5 Minutes
[] _LCM_ 'Green Board' check
[] _LCM_ Arm systems
T minus 10 seconds
[] _LCM_ ten second countdown to launch
T = 0
[] _Ignition_
[] _Tower_ Close-out crew activates Fire Supression plan
[] _Tower_ Close out crew secures tower and pad to post-launch state
[] _LCM_ Vehicle systems monitoring
[] _LCM_ Manual sequencing of vehicle if necessary
[] _LCM_ Dispatch recovery personnel to landing area
[] _Media/Spectators_ Relay information to media and spectators
[] _media/spectators_ Keep spectators from chasing after descending components of vehicle.
[] _Recovery Team_ stand ready to supress fire at landing area. Alert LCM to status at landing area.
[] open Champagne
-- ?LarryLeach - 02 Jun 2002