PSAS/ CapstoneLV2b/ capstone actual schedule
- Planner

Unnamed Project

Start: January 20, 2006
Finish: July 27, 2006
Report Date: April 3, 2006

Gantt Chart

WBS Name Work Week 4, 2006 Week 5, 2006 Week 6, 2006 Week 7, 2006 Week 8, 2006 Week 9, 2006 Week 10, 2006 Week 11, 2006 Week 12, 2006 Week 13, 2006 Week 14, 2006 Week 15, 2006 Week 16, 2006 Week 17, 2006 Week 18, 2006 Week 19, 2006 Week 20, 2006 Week 21, 2006 Week 22, 2006 Week 23, 2006 Week 24, 2006 Week 25, 2006 Week 26, 2006 Week 27, 2006 Week 28, 2006 Week 29, 2006
20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
1 Project Proposal Presentation 12d
1.1 Rough Draft ready for Andrew 5d
1.2 Rough Draft to Faust 3d
1.3 work out schedule details w/ Andrew 1d
1.4 project schedule 1d
1.5 finalize written proposal 2d
1.6 presentation slides/roles 2d
1.7 presentation dry run
1.8 proposal presentation
2 Choose Microcontroller 43d
2.1 discussion 29d
2.2 order microcontroller 14d
3 Spring break 7d
4 block diagram upgrade 6d
5 detailed schematic 14d
5.1 power supply block 14d
5.2 microcontroller block 14d
5.3 interface block 14d
6 Schematics design review + design interation 3d
7 final layout 9d
7.1 Package list + check availability 5d
7.2 board layout 7d
7.3 produce and check Gerbers 1d
7.4 validate 1d
8 Board design done
9 Order components 7d
10 FAB of board 3d
11 stuff board 7d
12 Prototype constructed
13 firmware 71d
13.1 learn eCos 20d
13.2 learn tool chain 10d
13.3 play with eval board 15d
13.4 queue scheme 1d
13.5 interrupt handler 10d
13.6 message handler 7d
13.7 flash firmware 3d
14 Firmware demo (first LED blink over CAN)
15 Test prototype 2d
15.1 voltage tests 4h
15.2 temperature tests? 4h
15.3 power consumption test 4h
15.4 noise test (RF) 4h
16 measure bus performance 8d
16.1 single channel bus test 4d
16.2 multiple (two?) channel bus test 4d
17 white paper 21d

Tasks

WBS Name Start Finish Work Priority Complete Cost Notes
1 Project Proposal Presentation Jan 20 Feb 3 12d
1.1 Rough Draft ready for Andrew Jan 20 Jan 25 5d 0%
1.2 Rough Draft to Faust Jan 26 Jan 28 3d 0%
1.3 work out schedule details w/ Andrew Jan 25 Jan 25 1d 0%
1.4 project schedule Jan 26 Jan 26 1d 0%
1.5 finalize written proposal Jan 30 Jan 31 2d 0%
1.6 presentation slides/roles Jan 30 Jan 31 2d 0%
1.7 presentation dry run Feb 1 Feb 1
1.8 proposal presentation Feb 3 Feb 3
2 Choose Microcontroller Feb 3 Mar 24 43d
2.1 discussion Feb 3 Mar 8 29d 0%
2.2 order microcontroller Mar 9 Mar 24 14d 0%
3 Spring break Mar 25 Apr 1 7d 0%
4 block diagram upgrade Apr 3 Apr 8 6d 0%
5 detailed schematic Apr 10 Apr 25 14d
5.1 power supply block Apr 10 Apr 25 14d 0%
5.2 microcontroller block Apr 10 Apr 25 14d 0%
5.3 interface block Apr 10 Apr 25 14d 0%
6 Schematics design review + design interation Apr 26 Apr 28 3d 0%
7 final layout Apr 29 May 9 9d
7.1 Package list + check availability Apr 29 May 4 5d 0%
7.2 board layout Apr 29 May 6 7d 0%
7.3 produce and check Gerbers May 8 May 8 1d 0%
7.4 validate May 9 May 9 1d 0%
8 Board design done May 9 May 9
9 Order components May 10 May 17 7d 0%
10 FAB of board May 18 May 22 3d 0%
11 stuff board May 23 May 30 7d 0%
12 Prototype constructed May 30 May 30
13 firmware Apr 3 Jun 23 71d
13.1 learn eCos Apr 3 Apr 25 20d 0%
13.2 learn tool chain Apr 26 May 6 10d 0%
13.3 play with eval board May 8 May 24 15d 0%
13.4 queue scheme May 31 May 31 1d 0%
13.5 interrupt handler Jun 1 Jun 12 10d 0%
13.6 message handler Jun 13 Jun 20 7d 0%
13.7 flash firmware Jun 21 Jun 23 3d 0%
14 Firmware demo (first LED blink over CAN) Jun 23 Jun 23
15 Test prototype May 31 Jun 1 2d
15.1 voltage tests May 31 May 31 4h 0%
15.2 temperature tests? May 31 May 31 4h 0%
15.3 power consumption test Jun 1 Jun 1 4h 0%
15.4 noise test (RF) Jun 1 Jun 1 4h 0%
16 measure bus performance Jun 24 Jul 3 8d
16.1 single channel bus test Jun 24 Jun 28 4d 0%
16.2 multiple (two?) channel bus test Jun 29 Jul 3 4d 0%
17 white paper Jul 4 Jul 27 21d 0%

Resources

Name Short name Type Group Email Cost Notes
Andrew Greenberg andrew Work andrew@uad.com 0
Glenn LeBrasseur glenn Work students glennl@twaves.org 0
Jacob Davidson jacob Work students jacobdav@gmail.com 0
Sarah Bailey sarah Work students saharabeara@gmail.com 0 On vacation from 03/23 (evening) to 01/02 (evening).