Agenda points:
- System update (with a live demonstration of the avionics system) 
- System integration issues: what's left? - More software debugging
- Test fit of camera prism/shroud/whatever
- TEST TO DO: 2nd system integration test:
- Live avionics system on rail on launch tower: total LT/LTC/FC/field server/ground laptops integration test
- Test reflected antenna power, GPS lock, etc.
- Some weekend - when?
- Second RF test: Monday November 8th
 
- Launch schedule - December 18th, January 8th.
- danger! danger! May be cancelled due to weather! in particular, snow/rain or low clouds
 
- Launch logistics: launch script, who's responsible for what, etc. - Put off until 2nd system test.
 
- Other issues - Road map
- Other group discussions (IP, security, etc).
 