<?xml version="1.0"?>
<project name="" company="" manager="" phase="" project-start="20060120T000000Z" mrproject-version="2" calendar="1">
  <properties/>
  <phases>
    <phase name="spec and design"/>
    <phase name="board construction"/>
    <phase name="testing"/>
    <phase name="optional"/>
  </phases>
  <calendars>
    <day-types>
      <day-type id="0" name="Working" description="A default working day"/>
      <day-type id="1" name="Nonworking" description="A default non working day"/>
      <day-type id="2" name="Use base" description="Use day from base calendar"/>
    </day-types>
    <calendar id="1" name="Default">
      <default-week mon="0" tue="0" wed="0" thu="0" fri="0" sat="0" sun="1"/>
      <overridden-day-types>
        <overridden-day-type id="0">
          <interval start="0800" end="1200"/>
          <interval start="1300" end="1700"/>
        </overridden-day-type>
      </overridden-day-types>
      <days>
        <day date="20060324" type="day-type" id="0"/>
        <day date="20060331" type="day-type" id="0"/>
        <day date="20060329" type="day-type" id="0"/>
        <day date="20060327" type="day-type" id="0"/>
        <day date="20060325" type="day-type" id="0"/>
        <day date="20060401" type="day-type" id="0"/>
        <day date="20060330" type="day-type" id="0"/>
        <day date="20060328" type="day-type" id="0"/>
      </days>
      <calendar id="2" name="sarah">
        <default-week mon="2" tue="2" wed="2" thu="2" fri="2" sat="2" sun="2"/>
        <overridden-day-types/>
        <days>
          <day date="20060324" type="day-type" id="1"/>
          <day date="20060331" type="day-type" id="1"/>
          <day date="20060329" type="day-type" id="1"/>
          <day date="20060327" type="day-type" id="1"/>
          <day date="20060325" type="day-type" id="1"/>
          <day date="20060401" type="day-type" id="1"/>
          <day date="20060330" type="day-type" id="1"/>
          <day date="20060328" type="day-type" id="1"/>
        </days>
      </calendar>
    </calendar>
  </calendars>
  <tasks>
    <task id="1" name="Project Proposal Presentation" note="" work="345600" start="20060120T000000Z" end="20060203T000000Z" work-start="20060120T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <constraint type="must-start-on" time="20060203T000000Z"/>
      <task id="2" name="Rough Draft ready for Andrew" note="" work="144000" start="20060120T000000Z" end="20060125T170000Z" work-start="20060120T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <constraint type="start-no-earlier-than" time="20060120T000000Z"/>
      </task>
      <task id="3" name="Rough Draft to Faust" note="" work="86400" start="20060125T170000Z" end="20060128T170000Z" work-start="20060126T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="2" type="FS"/>
        </predecessors>
      </task>
      <task id="4" name="work out schedule details w/ Andrew" note="" work="28800" start="20060125T000000Z" end="20060125T170000Z" work-start="20060125T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <constraint type="must-start-on" time="20060125T000000Z"/>
      </task>
      <task id="5" name="project schedule" note="" work="28800" start="20060125T170000Z" end="20060126T170000Z" work-start="20060126T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="4" type="FS"/>
        </predecessors>
      </task>
      <task id="6" name="finalize written proposal" note="" work="57600" start="20060128T170000Z" end="20060131T170000Z" work-start="20060130T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="5" type="FS"/>
          <predecessor id="1" predecessor-id="3" type="FS"/>
          <predecessor id="1" predecessor-id="2" type="FS"/>
        </predecessors>
      </task>
      <task id="7" name="presentation slides/roles" note="" work="57600" start="20060128T170000Z" end="20060131T170000Z" work-start="20060130T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <constraint type="start-no-earlier-than" time="20060127T000000Z"/>
        <predecessors>
          <predecessor id="1" predecessor-id="3" type="FS"/>
        </predecessors>
      </task>
      <task id="8" name="presentation dry run" note="" work="0" start="20060201T000000Z" end="20060201T000000Z" work-start="20060201T080000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
        <constraint type="must-start-on" time="20060201T000000Z"/>
        <predecessors>
          <predecessor id="1" predecessor-id="7" type="FS"/>
          <predecessor id="1" predecessor-id="6" type="FS"/>
        </predecessors>
      </task>
      <task id="9" name="proposal presentation" note="" work="0" start="20060203T000000Z" end="20060203T000000Z" work-start="20060203T080000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
        <constraint type="must-start-on" time="20060203T000000Z"/>
        <predecessors>
          <predecessor id="1" predecessor-id="8" type="FS"/>
        </predecessors>
      </task>
    </task>
    <task id="10" name="Choose Microcontroller" note="" work="547200" start="20060203T000000Z" end="20060224T170000Z" work-start="20060203T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <constraint type="start-no-earlier-than" time="20060204T000000Z"/>
      <task id="11" name="discussion" note="" work="144000" start="20060203T000000Z" end="20060208T170000Z" work-start="20060203T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="1" type="FS"/>
        </predecessors>
      </task>
      <task id="12" name="order microcontroller" note="" work="403200" start="20060208T170000Z" end="20060224T170000Z" work-start="20060209T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="11" type="FS"/>
        </predecessors>
      </task>
    </task>
    <task id="13" name="block diagram upgrade" note="" work="172800" start="20060208T170000Z" end="20060215T170000Z" work-start="20060209T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <constraint type="start-no-earlier-than" time="20060208T000000Z"/>
      <predecessors>
        <predecessor id="1" predecessor-id="11" type="FS"/>
      </predecessors>
    </task>
    <task id="14" name="detailed schematic" note="" work="403200" start="20060215T170000Z" end="20060303T170000Z" work-start="20060216T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="11" type="FS"/>
        <predecessor id="1" predecessor-id="13" type="FS"/>
      </predecessors>
      <task id="15" name="power supply block" note="" work="403200" start="20060215T170000Z" end="20060303T170000Z" work-start="20060216T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
      <task id="16" name="microcontroller block" note="" work="403200" start="20060215T170000Z" end="20060303T170000Z" work-start="20060216T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
      <task id="17" name="interface block" note="" work="403200" start="20060215T170000Z" end="20060303T170000Z" work-start="20060216T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
    </task>
    <task id="18" name="Schematics design review + design interation" note="" work="86400" start="20060308T000000Z" end="20060310T170000Z" work-start="20060308T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <constraint type="start-no-earlier-than" time="20060308T000000Z"/>
      <predecessors>
        <predecessor id="1" predecessor-id="14" type="FS"/>
        <predecessor id="1" predecessor-id="13" type="FS"/>
        <predecessor id="1" predecessor-id="10" type="FS"/>
      </predecessors>
    </task>
    <task id="19" name="final layout" note="" work="259200" start="20060310T170000Z" end="20060321T170000Z" work-start="20060311T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="18" type="FS"/>
      </predecessors>
      <task id="20" name="Package list + check availability" note="" work="144000" start="20060310T170000Z" end="20060316T170000Z" work-start="20060311T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
      <task id="21" name="board layout" note="" work="201600" start="20060310T170000Z" end="20060318T170000Z" work-start="20060311T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
      <task id="22" name="produce and check Gerbers" note="" work="28800" start="20060318T170000Z" end="20060320T170000Z" work-start="20060320T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="21" type="FS"/>
        </predecessors>
      </task>
      <task id="23" name="validate" note="" work="28800" start="20060320T170000Z" end="20060321T170000Z" work-start="20060321T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="22" type="FS"/>
        </predecessors>
      </task>
    </task>
    <task id="24" name="Board design done" note="" work="0" start="20060321T170000Z" end="20060321T170000Z" work-start="20060321T170000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="19" type="FS"/>
      </predecessors>
    </task>
    <task id="25" name="Order components" note="" work="201600" start="20060321T170000Z" end="20060329T170000Z" work-start="20060322T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="24" type="FS"/>
      </predecessors>
    </task>
    <task id="26" name="FAB of board" note="" work="86400" duration="115200" start="20060329T170000Z" end="20060403T170000Z" work-start="20060330T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-duration">
      <predecessors>
        <predecessor id="1" predecessor-id="25" type="FS"/>
        <predecessor id="1" predecessor-id="24" type="FS"/>
      </predecessors>
    </task>
    <task id="27" name="stuff board" note="" work="201600" start="20060403T170000Z" end="20060411T170000Z" work-start="20060404T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="26" type="FS"/>
      </predecessors>
    </task>
    <task id="28" name="Prototype constructed" note="" work="0" start="20060411T170000Z" end="20060411T170000Z" work-start="20060411T170000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="27" type="FS"/>
      </predecessors>
    </task>
    <task id="29" name="customize firmware" note="" work="691200" start="20060321T170000Z" end="20060418T170000Z" work-start="20060322T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="24" type="FS"/>
      </predecessors>
      <task id="30" name="queue scheme" note="" work="115200" start="20060321T170000Z" end="20060325T170000Z" work-start="20060322T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
      <task id="31" name="interrupt handler" note="" work="288000" start="20060325T170000Z" end="20060406T170000Z" work-start="20060327T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="30" type="FS"/>
        </predecessors>
      </task>
      <task id="32" name="message handler" note="" work="201600" start="20060406T170000Z" end="20060414T170000Z" work-start="20060407T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="31" type="FS"/>
        </predecessors>
      </task>
      <task id="33" name="flash firmware" note="" work="86400" start="20060414T170000Z" end="20060418T170000Z" work-start="20060415T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="32" type="FS"/>
          <predecessor id="1" predecessor-id="28" type="FS"/>
        </predecessors>
      </task>
    </task>
    <task id="34" name="Firmware demo (first LED blink over CAN)" note="&#10;" work="0" start="20060418T170000Z" end="20060418T170000Z" work-start="20060418T170000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="29" type="FS"/>
        <predecessor id="1" predecessor-id="28" type="FS"/>
      </predecessors>
    </task>
    <task id="35" name="Test prototype" note="" work="57600" start="20060411T170000Z" end="20060413T170000Z" work-start="20060412T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="28" type="FS"/>
      </predecessors>
      <task id="36" name="voltage tests" note="" work="14400" start="20060411T170000Z" end="20060412T120000Z" work-start="20060412T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="28" type="FS"/>
        </predecessors>
      </task>
      <task id="37" name="temperature tests?" note="" work="14400" start="20060412T120000Z" end="20060412T170000Z" work-start="20060412T130000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="36" type="FS"/>
        </predecessors>
      </task>
      <task id="38" name="power consumption test" note="" work="14400" start="20060412T170000Z" end="20060413T120000Z" work-start="20060413T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="37" type="FS"/>
        </predecessors>
      </task>
      <task id="39" name="noise test (RF)" note="" work="14400" start="20060413T120000Z" end="20060413T170000Z" work-start="20060413T130000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="38" type="FS"/>
        </predecessors>
      </task>
    </task>
    <task id="40" name="measure bus performance" note="" work="230400" start="20060418T170000Z" end="20060427T170000Z" work-start="20060419T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="35" type="FS"/>
        <predecessor id="1" predecessor-id="29" type="FS"/>
      </predecessors>
      <task id="41" name="single channel bus test" note="" work="115200" start="20060418T170000Z" end="20060422T170000Z" work-start="20060419T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
      <task id="42" name="multiple (two?) channel bus test" note="" work="115200" start="20060422T170000Z" end="20060427T170000Z" work-start="20060424T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
        <predecessors>
          <predecessor id="1" predecessor-id="41" type="FS"/>
        </predecessors>
      </task>
    </task>
    <task id="43" name="white paper" note="" work="604800" start="20060427T170000Z" end="20060522T170000Z" work-start="20060428T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
      <predecessors>
        <predecessor id="1" predecessor-id="40" type="FS"/>
        <predecessor id="1" predecessor-id="24" type="FS"/>
      </predecessors>
    </task>
  </tasks>
  <resource-groups default_group="1">
    <group id="1" name="students" admin-name="Andrew Greenberg" admin-phone="503-708-7711" admin-email="andrew@uad.com"/>
  </resource-groups>
  <resources>
    <resource group="1" id="1" name="Sarah Bailey" short-name="sarah" type="1" units="0" email="saharabeara@gmail.com" note="On vacation from 03/23 (evening) to 01/02 (evening)." std-rate="0" calendar="2"/>
    <resource group="1" id="2" name="Glenn LeBrasseur" short-name="glenn" type="1" units="0" email="glennl@twaves.org" note="" std-rate="0"/>
    <resource group="1" id="3" name="Jacob Davidson" short-name="jacob" type="1" units="0" email="jacobdav@gmail.com" note="" std-rate="0"/>
    <resource id="4" name="Andrew Greenberg" short-name="andrew" type="1" units="0" email="andrew@uad.com" note="" std-rate="0"/>
  </resources>
  <allocations/>
</project>